Request a DemoLog In(844) 692-0626
    • Americas
    • América Latina (Español)
    • Canada (English)
    • Canada (Français)
    • United States (English)
Request a DemoLog In
cta-construction-image

Take Your Knowledge to the Next Level

Choose from our library of free certification courses—start earning CE credits today.

Learn More

—  8 min read

Contract Precedence: A Clause to Clear Construction Confusion

By 

Last Updated Apr 15, 2024

Top of a construction contract document with tape measure and hard hat

Construction contracts are usually lengthy and complicated, composed of a wide range of documents In a perfect world, the contract provides the clarity and direction all stakeholders need to move forward on the project. Unfortunately, it’s not uncommon for contract documents to conflict with one another. For example, the drawing might specify one type of hardware for the doors, while the specs show another. And when contractors run into a conflict, how do they know which contract document to refer to?

Many contracts include a clause that lays out which documents take precedence, and in which order. This contract precedence clause provides clarity and serves as a useful tool if confusion arises. Let’s take a look at what contract precedence means: how it helps clear confusion, how precedence applies to different contract types — and alternatives to look at if dictating the order of precedence in construction contracts still leaves room for issues.

Contents

Table of contents

Setting the Precedent: Clarifying With This Clause

An order of precedence contract clause tells everyone involved in the project which documents supersede others. In some cases, the contract actually uses two clauses here. The first might simply state that contract precedence applies, while a sister clause lists out the order of precedence. In other contracts, these two clauses are combined into one.

Essentially, detailing the order of precedence in construction contracts provides a tie-breaker. If two pieces of information contained within the contract conflict, people can look to the contract precedence clause to point them toward which one to follow

This way, if a dispute arises during a construction project because of contradictory or ambiguous information within the contract documents, all parties have clarity around which documents trump others. Ideally, this eliminates confusion and resolves any conflict.

Enumerating the contract document list in the precedence clause can deliver extra clarity. For example, the individual drawing up the clause might include the version number and date of the drawing package that takes precedence. 

Contract Precedence Examples

To provide a clearer idea of the order of precedence in construction contracts, examples of precedence lists help. Here are a few contract precedence clause samples.  

In federal government work, the Federal Acquisition Regulation (specifically, FAR 52.215-8) governs the order of precedence to which contract documents apply. It says, “Any inconsistency in this solicitation or contract shall be resolved by giving precedence in the following order."

  1. Representations and other instructions
  2. Contract clauses
  3. Other documents, exhibits, and attachments
  4. The specifications

The Nebraska Department of Economic Development provides a Sample Construction Contract Provisions document. It states, “In the event of conflicts, the documents shall control in the following order of precedence.”

  1. Contract with latest, Addenda, Amendments, or Change Orders
  2. Request for Proposal with latest Amendments
  3. Plans, Drawings and Specifications
  4. Contractor’s Proposal

Michigan State University has published a version of the ConsensusDocs 200 Standard Agreement and General Conditions Between Owner and Contractor (Lump Sum Price). Section 14.2.5, the order of precedence clause, reads,  “In case of any inconsistency, conflict, or ambiguity among the Contract Documents, the documents shall govern in the following order.”

  1. Change Orders and written amendments to [this] Agreement 
  2. Agreement and General Conditions
  3. Subject to subsection 14.2.2 the drawings (large scale governing over small scale), specifications and addenda issued prior to the execution of this Agreement or signed by both Parties
  4. Information furnished by the Owner pursuant to subsection 3.13.4 or designated as a Contract Document in section 14.1
  5. Other documents listed in this Agreement. Among categories of documents having the same order of precedence, the term or provision that includes the latest date shall control. Information identified in one Contract Document and not identified in another shall not be considered a conflict or inconsistency.

Clearly, there are several approaches companies can take when applying contract precedence. The key thing to note is that a good contract precedence clause breaks the tie between two documents with competing or confusing information. 

Contract Precedence in Different Contract Types

Setting an order of precedence in construction contracts — or providing some other way to resolve conflicting information — is always important. But certain types of construction contracts make this especially critical. 

  • Lump Sum

    In a lump sum contract, for example, a single value gets affixed to the project. The owner wants to be certain that the work they expect can happen on that budget. At the same time, the general contractor (GC) and any subcontractors want to ensure they’re sufficiently compensated for their time and skills. As a result, all parties want to have a high level of clarity around the project to ensure the lump sum budget will work. A contract precedence clause plays a huge role here.

  • Time and Materials

    In a time and materials (T&M) contract, on the other hand, answering questions might have less financial impact. While there should still be a path to resolve confusion, stakeholders are less likely to run into major conflict because GCs and subs can bill for their time and materials. 

  • Guaranteed Maximum Price (GMP)

    Guaranteed maximum price projects generally operate on the assumption that the GC knows how to do the work that’s required. With that foundation and the fact that the GC is responsible for absorbing costs above the GMP, owners may be less concerned with clarifying clauses like contract precedence. 

Ultimately, though, any good construction contract builds in a way to clear up issues when they arise. 

Benefits of Order of Precedence Contract Clauses

Adding a contract precedence clause delivers the following perks for all stakeholders:

  • Clarity

    Guaranteed maximum price (GMP) projects generally operate on the assumption that the GC knows how to do the work that’s required. With that foundation and the fact that the GC is responsible for absorbing costs above the GMP, owners may be less concerned with clarifying clauses like contract precedence. 

  • Increased Work Efficiency

    When this clause exists, GCs and subs can refer to it when questions arise on the jobsite. Quickly learning that the specs take precedence over the drawings can point them to the right door hardware to install if the two documents conflict, for example. They can answer their question relatively rapidly and get back to work. 

  • Fewer Requests for Information

    Though requests for information (RFIs) are still useful if confusion persists, the contract precedence clause can clear up confusion, minimizing the number of RFIs on a project. 

  • Peace of Mind for Owners

    This clause allows project owners to determine what’s most important on the project and ensure compliance accordingly. They might give their request for proposal (RFP) precedence over the proposal the GC submitted, for example, to ensure that their desired project parameters hold weight if an issue comes up. 

All of this said, not all projects use an order of precedence contract clause. That’s partially because some in the industry have moved away from this option to other ways to provide clarification. 

Alternatives to Contract Precedence Clauses

Some leaders in the construction space, including the American Institute of Architects (AIA), now specifically advise against outlining order of precedence in construction contracts. 

In Section 1.2.1 of its Guide for Supplementary Conditions, including Amendments to AIA Documents A201 and the Owner-Contractor Agreements, the AIA says, “In the event of inconsistencies among the Contract Documents, the Architect is to interpret them to reflect the design intent. Establishing a fixed order of priority is not recommended because no one document constitutes the best authority on all issues that may arise.” 

When contract documents conflict, the stakeholder should move forward following whichever document lays out the highest standard specified in the contract. This clause hinges on clarity around which standard is higher, of course, so it’s not without its own issues.

Contracts should provide a means to clarity.

Ultimately, the order of precedence contract clauses and other similar clauses — like higher standard clauses — aim to resolve conflicts before they even begin by providing the requisite level of clarity. When companies have the bandwidth to do so, they can take a further step here.

To avoid conflicts that arise from a lack of contract clarity, companies can designate a person or team to harmonize the contract. Because the contract often contains documents from various teams — from legal to procurement to technical — having one dedicated pass-through of all of those documents together can help to discover (and ideally rectify) conflicts. 

The best construction projects are the ones on which everyone wins. Creating construction contracts that provide clear direction helps all stakeholders, from the owner to the sub who’s on the jobsite for just one day, to move forward on the same trajectory with the same goal in mind. 

Categories:

Preconstruction

Written by

Justin Vogel

Justin is a Senior Strategic Product Consultant for Procore. Justin has an extensive background in real estate development, construction engineering, and project management professional entrusted with high profile structures, and is involved in over $3.5 billion worth of construction representing developers, CEO's, GC's, equity partners, consultants, and attorneys in unique and complex pursuits.

View profile

Kacie Goff

Kacie Goff is a construction writer who grew up in a construction family — her dad owned a concrete company. Over the last decade, she’s blended that experience with her writing expertise to create content for the Construction Progress Coalition, Newsweek, CNET, and others. She founded and runs her own agency, Jot Content, from her home in Ventura, California.

View profile

Explore more helpful resources

article-image

Construction Contract Administration: Roles & Responsibilities

Construction contracts, especially for large projects, can be extremely detailed with many key documents often compiling thousands of pages. Because of this, larger firms have a dedicated role to keep...

article-image

Construction Contract Documents: 9 Key Components

Every construction project — whether a small-scale residential renovation or an extensive municipal development — requires a contract. Construction contracts are multifaceted, often comprising numerous documents that cumulatively define the...

article-image

Job Order Contracting (JOC) Explained

Contracts for commercial construction projects usually cover a complete scope of work, but large institutions often have ongoing needs for smaller projects. This is where job order contracting (JOC) comes...

article-image

The AIA A201 Explained for Contractors & Owners

Before beginning a project, owners, architects and contractors need to define and agree upon their relationship to each other, so that everyone’s expectations can be met. The AIA document A201...

Procore is committed to advancing the construction industry by improving the lives of people working in construction, driving technology innovation, and building a global community of groundbreakers. Our connected global construction platform unites all stakeholders on a project with unlimited access to support and a business model designed for the construction industry.

LinkedIn Icon
LinkedIn
Facebook icon
Facebook
Twitter icon
Twitter
Instagram Icon
Instagram
YouTube icon
YouTube

Call us at (844) 692-0626 to speak with a product expert.

Apple LogoApple App StoreGoogle Play logoGoogle Play

Downloads

Apple LogoApple App StoreGoogle Play logoGoogle Play
  • Privacy Notice
  • Terms of Service
  • Do Not Sell Personal Information

© 2024 Procore Technologies, Inc.