Inspection and Test Plans (ITPs): A Comprehensive Guide to Construction Quality Control
Last Updated Jul 30, 2025
Samantha Nemeny
17 articles
Sam—Samantha if she’s feeling particularly academic—has spent a decade in content marketing, with eight years focused on Australia’s construction industry. She has a knack for making complex ideas easy to understand, turning industry jargon into clear, engaging stories. With a background in SEO and marketing, she’s spent the past three years at Procore, helping industry professionals navigate the world of construction with content that’s both insightful and easy to digest.
Nicholas Dunbar
Content Manager
60 articles
Nick Dunbar oversees the creation and management of UK and Ireland educational content at Procore. Previously, he worked as a sustainability writer at the Building Research Establishment and served as a sustainability consultant within the built environment sector. Nick holds degrees in industrial sustainability and environmental sciences and lives in Camden, London.
Last Updated Jul 30, 2025

An Inspection and Test Plan (ITP) is far more than a compliance checklist - it’s a proactive quality control strategy that ensures every phase of a construction project meets the required standards. Think of an ITP as your project’s quality roadmap - it tells every trade where to stop, check and sign before moving on. By mapping out inspection and testing checkpoints from start to finish, an ITP helps mitigate risks, prevent costly rework, and streamline regulatory compliance.
In this guide, we’ll break down everything you need to know about ITPs - what they are, why they matter, how to create one, and how they drive efficiency and accountability in construction.
Table of contents
What Is an ITP in UK Construction?
An ITP is a structured quality assurance document detailing the specific inspections and tests required at different construction stages, such as welding or final building inspections, guiding teams to:
- Ensure each phase meets strict quality benchmarks.
- Identify compliance issues early, preventing costly delays.
- Minimise rework and unexpected project disruptions.
- Support a seamless project close-out.
While ITPs aren’t legally required, they’re often contractually mandated - especially on large-scale projects - because they help builders demonstrate compliance with the Building Regulations, key British Standards such as BS 5975 (temporary works) and BS EN ISO 9001 (quality management). Beyond compliance, they serve as a safeguard for quality, reducing defects and ensuring construction integrity.
How Is an ITP Used in Construction?
ITPs integrate into project workflows to verify that quality and compliance requirements are met at key phases.
Planning & Development
- Quality Engineers draft the ITP, ensuring all required inspections are covered.
- Construction and Quality Managers refine the plan, oversee its implementation, and track compliance.
- Main Contractors & Subcontractors help identify hold points and quality benchmarks.
- Clerk of Works / Site Engineer reviews workmanship on behalf of the client and signs hold-points.
Pre-Construction Implementation
- The ITP is shared with all stakeholders - contractors, site teams, and inspectors - to ensure alignment.
- Owners & Developers may review the plan to confirm quality control measures are in place.
- Training on inspection procedures and documentation is conducted as needed.
Execution & On-Site Inspections
- Contractors & Engineers perform inspections and tests at key project checkpoints.
- Quality Managers oversee compliance and address any defects before work progresses.
- Regulators or Third-Party Inspectors may conduct audits or witness critical inspections.
Final Verification & Handover
- The main contractor compiles and signs off on the ITP.
- Owners & Developers review documentation to ensure all inspections and tests have been completed before taking possession.
- Digital tracking tools can be used to streamline reporting and record-keeping.
By integrating inspections throughout the project lifecycle, ITPs prevent defects, improve accountability, and ensure regulatory compliance.
The Importance of ITPs in Construction
An effective ITP strengthens quality control, risk management, and compliance:
- Risk mitigation. ITPs help prevent delays, disputes, and costly rework by establishing clear inspection checkpoints and improving accountability.
- Quality assurance. ITPs ensure that materials, workmanship, and installation meet project specifications.
- Regulatory compliance. ITPs help contractors align with the Building Regulations, British Standards, CDM 2015, and the Building Safety Act 2022, reducing the risk of compliance failures.
- Data-driven decision-making. By tracking inspections and test results, teams can identify trends and adjust quality processes in real time.
- Improved efficiency and collaboration. With standardised inspection processes, teams work more effectively, reducing miscommunication and improving coordination.
How Technology Improves ITP Tracking and Compliance
Traditional paper-based ITPs can be cumbersome, leading to misplaced documents and communication gaps. Digital solutions enhance efficiency by:
- Automating workflows. Cloud-based platforms notify teams of upcoming inspections and flag missed hold points.
- Centralising documentation. Inspection records, photos, and test results are stored in one place for easy access and auditing.
- Providing real-time updates. Mobile apps allow teams to conduct inspections on-site, upload reports instantly, and receive immediate feedback.
- Integrating with project management software. Digital ITPs link to broader construction programmes, ensuring quality checks align with project milestones.
- Enhancing compliance tracking. AI-powered analytics can detect patterns in test results, identifying potential quality issues before they escalate.
By digitising ITPs, contractors cut rework (risk mitigation), save admin hours (efficiency) and surface live dashboards for site teams (data-driven decisions).
Learn about the future of the built environment - Read Procore's Future State of Construction report
Learn how contractors, subcontractors, and project teams can take advantage of new opportunities to boost efficiency and profitability over the next decade. Download the report to get your roadmap to the future state of construction.

What’s Included in an Inspection and Test Plan?
Here’s what you’ll find in a typical ITP document:
- Inspection tasks: Specifies key areas like structural integrity, fire safety, and electrical compliance.
- Quality checkpoints: Establishes acceptance criteria for materials and workmanship.
- Safety and compliance: Outlines adherence to Building Regulations, BS/EN standards, CDM 2015, and contractual requirements.
- Reporting and documentation: Details how inspections are recorded and approved.
Most ITPs follow standardised templates and often include visual aids, checklists, or infographics to streamline quality control across multiple projects.
How to Create an Effective ITP
A structured approach ensures an ITP is comprehensive, practical, and compliant.
1. Define the Scope of the ITP
Identify requirements and applicable codes, including:
- British Standards (e.g., BS 5975, BS EN ISO 9001)
- Building Regulations (Parts A – P)
- The Building Safety Act 2022 and CDM 2015 duties
- Contractual quality standards
2. Identify Inspection and Testing Activities
Break the project into work stages (e.g., material receipt, welding, installation) and specify required inspections at each stage.
For instance, after completing fabrication, you may conduct a fit-up inspection before moving forward to welding.
3. Define Inspection and Test Methods
Specify how inspections will be conducted, such as:
- Visual inspection (e.g., surface defects, alignment)
- Non-Destructive Testing (NDT) (ultrasonic, radiography, magnetic particle testing)
- Destructive testing (tensile strength, impact testing)
- Functional testing (pressure test, load test)
- Dimensional verification (measuring tolerances)
Set pass/fail criteria for each test.
4. Assign Responsibility
Clarify who is responsible for each test and approval, whether it’s the head contractor, a third-party inspector, or a regulatory body.
5. Identify Hold, Witness and Review Points
Determine critical inspection stages:
- Hold Points (H): Work cannot proceed until inspection approval.
- Witness Points (W): The client or inspector is invited to witness but work may continue if they do not attend.
- Review Points (R): Documentation must be reviewed before approval.
6. Define Records and Documentation Requirements
Specify what records are needed, such as:
- Inspection reports
- Inspection Test Certificates (ITCs)
- Photographic records
- Calibration certificates
7. Develop the ITP Table
A structured table makes ITPs easier to follow. Example:
Activity | Inspection /Test Method | Acceptance Criteria | Responsible | Hold / Witness / Review | Records |
Material Receipt | Visual Inspection | No visible defects | Contractor | H | Report |
Welding | NDT - Ultrasonic Test | BS EN ISO 17640 | Third-Party Inspector | W | NDT Report |
Pressure Testing | Hydrostatic Test | 1.5x design pressure | Contractor/TPI | H | Test Certification |
8. Review and Approve the ITP
Finally, the ITP must be reviewed and approved by all stakeholders before it can be implemented.
FAQ
ITP vs Checklist
An ITP is a project-wide roadmap; a checklist is a task-level to-do. The ITP may contain many checklists.
What is ITC?
An ITC (Inspection Test Certificate) is the evidence produced once an ITP hold-point passes.
Maintain quality control with ITPs.
A well-structured ITP is more than a regulatory tool; it ensures quality, reduces risk, and enhances project efficiency. By leveraging digital solutions, construction teams can streamline compliance tracking, improve collaboration, and proactively manage quality across every phase. In an industry where delays and defects can be costly, an effective ITP is essential to delivering projects on time, within budget, and to the highest standards.
Categories:
Tags:
Written by
Samantha Nemeny
17 articles
Sam—Samantha if she’s feeling particularly academic—has spent a decade in content marketing, with eight years focused on Australia’s construction industry. She has a knack for making complex ideas easy to understand, turning industry jargon into clear, engaging stories. With a background in SEO and marketing, she’s spent the past three years at Procore, helping industry professionals navigate the world of construction with content that’s both insightful and easy to digest.
View profileReviewed by
Nicholas Dunbar
60 articles
Nick Dunbar oversees the creation and management of UK and Ireland educational content at Procore. Previously, he worked as a sustainability writer at the Building Research Establishment and served as a sustainability consultant within the built environment sector. Nick holds degrees in industrial sustainability and environmental sciences and lives in Camden, London.
View profileExplore more helpful resources

A Guide to Construction Risk Assessments in the UK
Construction is one of the United Kingdom’s most dynamic industries, driving economic growth, shaping skylines and creating essential infrastructure. But with opportunity comes risk. From worker safety to cost pressures...

Construction Cash Flow Forecast: A Step-by-Step Guide
In construction, sound financial management revolves around the cash flow strategy: knowing when money will come in, how much will go out, and whether the gap between the two is...

Holistic Portfolio Insights for Proactive Resource and Cost Management in Construction
Holistic portfolio insights help teams to get an understanding of progress, costs, resources and more. Construction companies rely on insights into their portfolios to make proactive decisions about their projects...

Mastering the Critical Path: A Guide to CPM in Construction
While every task must be completed to complete a construction project, some tasks are more critical than others. It’s crucial to be able to identify which activities must be finished...