— 9 min read
Security of Payments Act Western Australia (WA): What Contractors Need to Know
Last Updated Jun 8, 2025

Timely payments are critical for keeping projects on track and protecting subcontractors from cash flow issues.
In Western Australia, The Building and Construction Industry (Security of Payment) Act 2021 s provides contractors and suppliers with a clear legal pathway to secure payments, without needing to escalate to court.
It gives contractors the legal right to be paid as the job progresses, and explains exactly how to ask for payment, respond to a claim, and get help if there’s a dispute.
Key Rights Under the West Australia’s Security of Payment Act
Under the Security of Payment Act (SOPA), eligible claimants in WA can:
- Progress payments: Contractors can claim for construction work or related goods/services, even if the contract doesn’t allow for it
- Right to issue a payment claim: Claims must identify the contract, describe the work or goods supplied, show the amount claimed and how it was calculated, and reference the Act
- Obligation to provide a payment schedule: Respondents must reply within the earlier of the contractual timeframe or 15 business days, and justify any withheld amounts
- Adjudication pathway: If payment is delayed or underpaid, claimants can apply for adjudication without going through court
- Debt recovery mechanism: Adjudicated or scheduled amounts not paid on time can be recovered as a debt in court
- Automatic liability for non-response: If a payment schedule isn’t provided on time, the respondent is liable for the full amount claimed
- Right to suspend work: Contractors can suspend work if unpaid, without being held responsible for resulting project delays
- Interest on overdue payments: Interest is payable at either the contract rate or the rate under the Civil Judgments Enforcement Act 2004, whichever is higher
- Review by a second adjudicator: Certain determinations can be reviewed, provided the disputed amount is paid into trust
In addition, “Pay when paid” clauses are banned. This means payment cannot be made conditional on the contractor or builder receiving funds from another party.
Note: This article is intended as a general guide only and doesn’t replace legal advice. If you're unsure about your situation, it's best to speak with a qualified legal professional.
Table of contents
Who Can Make a Claim?
In Western Australia, any party performing construction work or supplying related goods and services under a construction contract may claim a progress payment.
This includes:
- Head contractors: Claiming against project principals
- Subcontractors: Claiming against head contractors
- Suppliers and consultants: Providing construction-related goods or services
The right to claim exists regardless of whether the contract includes explicit payment provisions, but many subcontractors struggle with the business know-how needed to understand or act on these rights.
Pro Tip
Residential work is partially excluded. The Act does not apply to home building contracts that meet all of the following conditions:
Principal is an individual: Not a business or developer
Contract value is under $500,000: Or another amount set by regulation
Work is not for multiple dwellings or part of a residential development business
Contract is not between contractors/subcontractors: It must be a direct agreement between a builder and homeowner
Larger-scale or subcontracted residential work may still be covered if these conditions aren’t met. These exemptions make WA’s residential coverage more limited than states like NSW, where most residential building contracts are included.
What Work can be Claimed?
The Security of Payments Act (SOPA) 2021 covers a broad range of construction work and related services performed under contract in Western Australia.
It provides clear definitions to ensure wide industry coverage, including both physical works and professional services.
Claimable work includes:
Construction work
- Building, extending, altering, repairing, maintaining, demolishing, or removing structures or civil works
- Roads, railways, bridges, tunnels, pipelines, dams, ports, and other major works
- Electrical, plumbing, HVAC, fire protection, lighting, sanitation, security, communications, lifts, and escalators
- Excavation, earthworks, scaffolding, site restoration, landscaping, painting, and on-site cleaning
Related goods and services
- Materials: Supplied goods or components that form part of the work
- Plant and equipment: Hired for use in carrying out the work
- Professional services: Architecture, engineering, surveying, design, interior, and landscape consulting
The SOPA also outlines what kinds of work can’t be claimed, which include:
- Mining-related activity, such as the construction of pits, shafts, or quarries for oil, gas, or mineral extraction
- Work performed under a contract of employment
- Contracts that form part of a loan, guarantee, or insurance arrangement
- Non-cash contracts, where payment isn’t tied to the value of work or goods supplied
- Work carried out outside WA
Timeframe and Deadlines
The Security of Payments Act (WA) sets out strict timeframes for issuing claims, providing payment schedules, and initiating adjudication. Missing these deadlines can result in lost rights or automatic liability.
Default Payment Deadlines
If the contract doesn’t specify earlier dates, the following statutory defaults for payments apply:
- Principal to head contractor: Within 20 business days after the payment claim is served
- Head contractor to subcontractor: Within 25 business days after the payment claim is served
Serving a Payment Claim
Payment claims can be made:
- On or after the end of the month in which work or supply occurred, unless the contract allows earlier claims
- After termination of the contract
- Within the later of the timeframe in the contract or 6 months after the last work or supply
For final payments, claims can be made up to 28 days after the defects liability period or 6 months after completion, whichever is later. Unless otherwise agreed, only one claim can be made per named month.
Providing a Payment Schedule
Respondents must issue a payment schedule within the earlier of 15 business days or the timeframe stated in the contract.
If a payment schedule isn’t served on time, the respondent becomes liable for the full claimed amount and loses the right to respond in adjudication.
Applying for Adjudication
Application deadlines depend on how the respondent acts:
- If a schedule is issued but underpays: Apply within 20 business days after receiving the schedule
- If the scheduled amount isn’t paid on time: Apply within 20 business days after the due date
If no schedule is issued and no payment is made:
- Serve a notice of intent to adjudicate within 20 business days of the due date
- Wait 5 business days for a response
- If no schedule is received, apply within 20 business days after that response period ends
Post-Adjudication Payment
If no specific due date is stated in the adjudication decision, payment must be made within 5 business days of receiving the determination.
The Payment Claim Process
The SOPA outlines a clear process for claiming and recovering payment. Each step must be followed precisely to stay compliant and preserve enforcement rights.
Prepare the Payment Claim
The payment claim must:
Describe the construction work or related goods/services being claimed
State the amount claimed, including retention or performance security if applicable
Clearly state that it is made under the Act
There is no requirement in WA for head contractors to include a supporting statement about subcontractor payments, as is the case in many other states.Serve the Payment Claim
Claims must be delivered using an approved method, such as hand delivery, post, or another contract-specified method. Email is acceptable if agreed. Timing must comply with:
The claim period specified in the contract, or
The legislative defaults (typically monthly, or up to 6 months after last work/supply for progress claims)
Only one claim can be made per named month unless otherwise agreed.Respondents Must issue a Payment Schedule
Respondents must issue a payment schedule that:
Identifies the related payment claim
States the scheduled amount they propose to pay
Explains why any amount is withheld, if relevant
This must be provided within the earlier of:
15 business days, or
The timeframe stated in the contract
If no payment schedule is served on time, the respondent becomes liable for the full amount claimed and may lose the right to respond in adjudication — a risk that’s often overlooked when payment processes rely on informal communication.Respondent Pays or Claimant Takes Action
The respondent must pay the scheduled amount by the due date
If unpaid, the claimant may recover the amount as a debt in court, apply for adjudication, and suspend work after giving 2 business days’ notice
If no schedule is issued and no payment is made:
The claimant must serve a notice of intent to apply for adjudication within 20 business days of the missed payment due date
The respondent has 5 business days to issue a payment schedule
If none is provided, the claimant can then apply for adjudication
The application must be made within 20 business days after this entitlement arisesAdjudication (if required)
If the scheduled amount is unpaid or is less than claimed, the claimant may apply for adjudication. The adjudicator will review the payment claim, schedule (if any), and any supporting evidence, then issue a binding determination.
Payment or Enforcement
If the adjudicated amount is not paid:
The claimant may request a certified determination and file it in court as a judgment debt
The respondent cannot raise new defenses or counterclaims, unless appealing on the basis of jurisdictional error
The claimant may suspend work with appropriate notice
Payment must be made by the date in the adjudication determination or within 5 business days of the determination being received, if no date is specified.
What Happens After You Make a Claim?
Once a valid payment claim is served, the next move belongs to the respondent.
Payment Schedule Deadline
The respondent must provide a payment schedule within the earlier of:
- 15 business days after receiving the claim, or
- The timeframe specified in the construction contract
What the Payment Schedule Must Include
The schedule must:
- Identify the relevant payment claim
- State the amount the respondent proposes to pay (the “scheduled amount”)
- Explain why any amount is withheld, if paying less than claimed
If the respondent intends to dispute the claim, they must state their reasons now. New reasons can’t be introduced later during adjudication.
If No Payment Schedule is Provided
The respondent becomes liable to pay the full amount claimed by the due date for the progress payment. If payment isn’t made, the claimant has enforcement options.
If Payment isn’t Made (With or Without a Schedule)
The claimant may:
- Recover the unpaid amount as a debt in court (limited to situations where a payment schedule proposed a non-zero amount)
- Apply for adjudication (available whether or not a payment schedule was issued)
- Suspend work or supply (available in either case, with 2 business days’ written notice
Adjudication
Adjudication is a fast-track dispute resolution process under the SOPA 2021. It allows contractors and suppliers to resolve payment disputes quickly, without going to court.
A claimant can apply for adjudication if:
- The scheduled amount is less than the claimed amount
- The respondent fails to pay the scheduled amount by the due date
- No payment schedule is issued, and the full claimed amount remains unpaid by the due date (after following the required notice process)
Understanding WA’s Security of Payment Act is essential for protecting your right to prompt and fair payment
The Building and Construction Industry (Security of Payment) Act 2021 provides a clear legal framework for making, responding to, and enforcing payment claims. Knowing your rights, deadlines, and enforcement options helps reduce disputes and safeguard cash flow.
Categories:
Tags:
Written by
Tom Proctor
13 articles
Before joining the world of technology, Tom worked as a Contract Administrator. This hands-on experience gives him a unique perspective that he leverages in his current role at Procore, where he has been for the past two years. Tom is passionate about helping construction businesses understand best practices around project management solutions and the many benefits they can provide.
View profileMiles Cope-Summerfield
I'm a Strategic Product Consultant at Procore with a passion for delivering creative solutions through software. At Procore, I wear multiple hats, working in consulting, change management, product management, sales and customer success. Currently I work with Enterprise clients to consult on processes and drive Procore’s evolution as a market leader. My four years in construction/engineering equipped me with skills to combine technical knowledge with real world experience. During this time I grew a passion for sustainability through completing life cycle analyses on sustainable timber construction, and designing with modern technologies to promote eco-friendly solutions.
View profileExplore more helpful resources

Mastering Subcontractor Management: Tips for Smoother, More Profitable Projects
Subcontractor management directly impacts project quality, timelines, and profitability. Strategic oversight reduces risk and keeps work running on schedule while maintaining budget control. This article explores the essential components of...

Design Once, Use Twice: Better Documentation for Circular Construction
Construction consumes massive volumes of raw materials and resources. According to the Green Building Council of Australia, nearly 50% of all the world’s resource use is in some way associated...

Security of Payment Act Tasmania (TAS): What Contractors Need to Know
Understand your rights and obligations under NSW’s Security of Payment laws to get paid on time and protect your cash flow. Delayed payments put subcontractors at financial risk and stall...

Security of Payment Act South Australia (SA): What Contractors Need to Know
Understand your rights and obligations under SA’s Security of Payment laws to get paid on time and protect your cash flow. Late payments strain cash flow, delay projects, and put...