Ctrl + Build: The Data Centre Balancing Act – Why Commissioning Risk is the Biggest Blind Spot in Today’s Builds
Last Updated May 23, 2025

This is the first instalment of Ctrl + Build — Procore’s new series exploring the fast-moving, complex, high-stakes world of data-centre construction. From commissioning risk to carbon strategy, we’re uncovering what it takes to build smarter, safer and sharper facilities.
Data centres may look like simple structures – steel, slab and services – but inside they are complex, high-stakes, precision-built environments. That paradox exposes contractors to risk, especially during commissioning.
Table of contents
What Makes Data Centres Different?
The explosion in data demand is fuelling a global boom in data-centre construction.
“Exponential” is an over-used term – but in this case it really is accurate. The pace of investment in data centres has become almost impossible to quantify; each new report offers an estimate larger than the last.
Artificial intelligence, cloud computing, crypto-mining and the Internet of Things are driving ever-greater demand for processing power – and the supporting infrastructure must scale rapidly in response.
An ecosystem of hyperscalers, developers, equipment manufacturers, utilities providers and infrastructure investors is coalescing around three clear objectives: scalability, reliability and efficiency.
The stakes are high and speed-to-market is critical. In the race to meet demand, delivery risk is escalating. While many contractors see data centres as just another infrastructure project, those who have delivered them before know the biggest risks lie where you least expect them.
Most of the project is still to be built once the façade goes up. Services are the most complex part of a data-centre build – and sometimes account for up to 70% of the project’s cost.
Simon Baker
Procore
Not in the structure, but in the systems. Not in the slab, but in the services. And especially, in the final mile that brings it all together: commissioning.
More Than Meets the Site
At first glance, a data centre may seem like a tin shed on a concrete slab. But behind the façade lies critical systems built for uptime, security and scale.
That’s why data centre delivery is about more than speed. It’s about precision. Nowhere is that more critical than in the final mile: commissioning. Consider:
- Uptime requirements: Tier 4 data centres aim for 99.995% uptime per year – that’s less than 26 minutes downtime. Missed commissioning steps or service faults can compromise this from day one.
- Redundancy layers: Most data centres have duplicate systems to ensure uptime. Managing these adds considerable complexity to design, commissioning and testing.
- Data security protocols: With hyperscale clients often housing sensitive or regulated data, any contractor working on a data centre build may be required to meet ISO 27001 compliance to ensure architectural, engineering and operations plans do not fall into the wrong hands.
Commissioning isn’t just the final step — it’s the tipping point between a functioning facility and a stalled investment.
Table 1: Data Centre Tiers and Reliability Standards
Tier | Uptime Guarantee | Annual Downtime | Key Feature |
1 | 99.671% | Up to 28.8 hrs | Basic backup |
2 | 99.741% | Up to 22 hrs | Redundancy for critical systems |
3 | 99.982 | Up to 1.6 hrs | Fully redundant and maintainable |
4 | 99.995 | Less than 26 minutes | Fault-tolerant infrastructure |
Sources: Uptime Institute, 2025; Uptime.is, 2025; Data Centre Info, n.d.
The Hidden Risk of Commissioning
Commissioning – the process of testing and verifying every system before go-live – is the most critical phase of a data centre build. Yet it is also the phase most likely to cause costly delays. Just some of the reasons include:
- Incomplete inspections: Systems can’t be certified for use unless every element has been reviewed and approved, often across multiple trades.
- Poor documentation: Paper-based defect lists or scattered spreadsheets lead to gaps in asset registers and inspection records.
- Service clashes: Mechanical, electrical and fire protection systems may interfere with each other if not coordinated upfront.
- Delayed utility integration: Power or data feeds from external providers may not be ready when needed.
- Lack of digital handover planning: Without a clear digital quality assurance process, key steps are missed, leading to retesting and rework.
Commissioning delays can add an average of 4–6 weeks to the delivery timeline, says Procore Solutions Engineer Simon Baker.
Even a week-long delay in commissioning could represent millions in lost value, and reputational damage that’s much harder to quantify.
Maryrose Walsh
On high-stakes hyperscale builds, the cost of sitting idle can be staggering. According to some estimates, hyperscale data centres can generate US$1 million per minute in revenue – meaning delays or outages can cost just as much.

Source: Uptime Intelligence Data Survey, 2024
Why Builders Fall Short
Traditional contractors, regardless of their experience, often approach data centre builds with a mindset shaped by commercial towers or warehouses. That works fine – until they reach commissioning. Why? Because:
- Service integration is not standardised across the industry
- Many subcontractors lack experience in high-precision environments
- Too many builders still rely on paper-based processes and ad hoc tracking tools.
In one extreme example, Simon Baker worked on a fully built data centre that was left idle for months because co-ordination with the utility provider fell through. The project had no power – and no Plan B.
What Better Looks Like
Three-quarters of customers that use Procore report an average 16% reduction in rework. This is a key metric for all contractors, but especially for data centre project teams looking to hit the “right first time” standard that hyperscale clients now demand, Maryrose notes.
The bottom line? In data centre delivery, the finish line is not just handover; it is performance from the first minute of uptime.
The best data centres do not just run well — they start right. Commissioning is where it all comes together, but success depends on setting up the right systems and workflows from day one.
Simon Baker
Procore
Commissioning remains the most under-recognised – and most consequential – risk in data centre delivery. Builders with a background in structure rather than services are especially vulnerable, often under-estimating the complexity of commissioning until it is too late.
The way forward is clear: standardisation, early service co-ordination and digital workflows are essential to mitigating delays, avoiding costly re-work and protecting project margins. Real-time data captured during commissioning empowers smarter scheduling, forecasting and decision-making across the project life-cycle.
By connecting every stakeholder to a single source of truth, Procore helps data centre project teams achieve greater visibility, accountability and trust — driving sharper project outcomes and faster speed-to-revenue.
Categories:
Tags:
Written by
Simon Baker
Simon Baker is a Solutions Engineer at Procore Technologies, where he helps construction businesses across Australia and New Zealand drive efficiency and innovation through technology. Before joining Procore, Simon built a strong foundation in the construction industry, working as a Service Coordinator at Construction Services and Infrastructure, where he was involved in delivering Data Centre projects across Australia. Earlier in his career, Simon spent nearly eight years as an electrician at Castle Electrical & Solar, where he completed his apprenticeship and led residential and commercial projects, including level 2 electrical works and solar and battery installations. With hands-on project management experience and a deep understanding of building services, Simon is passionate about empowering construction teams to deliver better outcomes through smarter processes and technology.
View profileMaryrose Walsh
Maryrose is the Manager of Enterprise Solutions Engineering at Procore and is dedicated to transforming the construction industry through innovative technology solutions. With a life long career in Pre Sales spanning many industries, she has a strong technical foundation in software architecture, integration, and scalable platforms. Bringing this rich experience to Procore, Maryrose excels at aligning complex solutions with the real-world needs of construction businesses through her customer first mindset and strategic approach. With her passion for driving innovation and efficiency, she is dedicated to collaborating with construction organisations to achieve transformative outcomes through technology.
View profileReviewed by
Nicholas Dunbar
44 articles
Nick Dunbar oversees the creation and management of UK and Ireland educational content at Procore. Previously, he worked as a sustainability writer at the Building Research Establishment and served as a sustainability consultant within the built environment sector. Nick holds degrees in industrial sustainability and environmental sciences and lives in Camden, London.
View profileExplore more helpful resources

AI in Construction and the Built Environment
Artificial intelligence (AI) will transform UK construction and how we assess and interact with our built environment, bringing new efficiencies and insights once difficult to imagine. AI technologies now embed...

How Construction Companies Can Drive Value from Automation
Most of us use automation in our day-to-day lives, even if we might not realise it. Robot vacuum cleaners, email scheduling tools, contactless payments and navigation apps are all examples...

How Construction Project Management Drives Project Success
Construction is widely acknowledged as one of the most complex and rapidly evolving industries in the world. Beyond bricks and mortar, it calls for precision planning, close coordination, and expert...