Request a DemoLog In1800 431 456
    • Asia Pacific
    • Australia (English)
    • Singapore (English)
Request a DemoLog In

—  5 min read

Construction Purchase Orders 101: A Contractor’s Guide to POs

By 

Last Updated Dec 8, 2023

2 contractors wearing PPE at construction site surveying amount of concrete needed for concrete pour

Construction purchase orders are key financial elements of an overall project contract. In construction specifically, a purchase order (PO) is typically validated by two parties: the buyer and seller. The buyer (usually an owner or head contractor) issues a PO to the seller (usually a head contractor or speciality contractor) to cover the cost of the project. 

The document outlines the price and quantity of goods or services necessary to complete the project contract as agreed upon by both parties. 

Contents

Table of contents

Information in a Construction Purchase Order

In order to illustrate the contents of a construction purchase order and how they are relevant to the completion of a project, let’s use a hypothetical scenario featuring Jane and John. Let’s say Jane is a project manager at a HC hired to build a warehouse while John is a concrete contractor who won the tender to pour the foundation of that warehouse.

Description of Deliverables

Upon receiving the tender for the concrete pour, John and his team visit the site. They identify the tools, equipment, materials and labour needed to complete the project. Once he relays that information to the HC, Jane’s team will draft a PO for the deliverables outlined by John and his team. 

Number of Deliverables

As Jane’s team is drafting the PO, they have to be diligent with listing the quantities for each deliverable provided by John. This is important because a PO explicitly states the HC’s fiscal responsibility for the deliverables needed to complete the work expected of the speciality contractor. This document, therefore, protects both parties by ensuring that:

  1. The HC receives the amount and quality of work requested.
  2. The SC gets paid for the items needed to complete the work requested.

Agreed-Upon Cost

As Jane’s team lays out the itemised list of deliverables requested by John’s team, the two parties will agree on a cost per item and possible discounts for certain quantities of those items. 

Terms of Payment

The terms of payment for a construction purchase order are usually based on credit. The HC sends the PO to the SC to request a service on credit. This protects the HC in the event that payment is given before the completion of the project. 

The terms of payment can also be set in regards to a net payment term. It defines how many days after a progress claim is submitted the buyer has to make the payment. In this scenario, we will say that Jane approves a PO with a net 30 term, which means John will be paid within 30 days of submitting a progress claim for the completed work. 

Due Dates

Now that the parties have agreed to the terms of payment, Jane and Johns’ teams will decide on due dates for the deliverables requested in the PO. These dates will inform the date of delivery of those deliverables.  

Method of Delivery

One of John’s deliverables in the PO is an extra concrete mixer that has to be delivered from a different territory. The delivery method for that mixer will typically be defined as one of two FOB (Free On Board) shipping terms: FOB Shipping Point (or FOB Origin) and FOB Destination. If “FOB Origin” is agreed upon, the HC will become responsible for any loss or damages incurred to the mixer as soon as it leaves the warehouse and is in transit to the worksite. If “FOB Destination” is agreed upon, the SC will be responsible for any damage incurred to the mixer until it reaches the worksite. 

Reference Numbers

The reference number is one of the most important pieces of the construction purchase order—it helps track the document. Since a project can have hundreds of PO’s attached to it, they can commonly become lost or jumbled during a project’s lifetime. The only way to prove that a service or material was completed or delivered as requested is to be able to locate the respective PO by its reference number. 

Purchase Order vs Progress Claim

There is one main difference between a construction purchase order and a progress claim. A PO is submitted by the buyer (Jane the HC) to determine the cost of a contract before the work is completed. In contrast,  a progress claim is submitted by the seller (John the SC) after the work is completed to receive an agreed-upon payment.

Purchase Order vs Contract

The difference between a construction purchase order and a contract is that a contract is a legally binding document that covers products, agreed prices and payment terms, and conditions for the entirety of a construction project. It includes all necessary purchase orders (documents that outline the price and quantity of goods or services necessary to complete the project contract) and progress claims.

Pay Attention to PO Details

A construction purchase order is a key item in a project contract because it’s a legally binding document that protects both the buyer and seller of a product or service. When drafting a PO, it’s important to remember to be explicit and detailed when filling out the following sections:

  • Description of deliverables,
  • Number (or quantity) of deliverables,
  • Agreed-upon cost,
  • Terms of payment,
  • Due dates,
  • Method of delivery,
  • Reference Numbers.

Categories:

Tags:

Written by

Emma De Francesco

16 articles

Emma is currently Strategic Product Consultant at Procore where she loves partnering with clients to help them achieve the best possible results. She has worked as a Project Manager in previous roles, responsible for overseeing small to medium-sized projects across various sectors including commercial, health and lifestyle, retail, government and hotels. Throughout these projects, she managed everything from project costs, program and quality & safety, to design management, procurement, and authority approvals.

View profile

Explore more helpful resources

article-image

Construction Defect Lists Explained

A defect list is a document that lists the final tasks remaining before a construction project — or scope of work — is considered complete. Builders add all work that...

article-image

Construction Estimating: The Building Blocks to Success

Construction estimating is a crucial process in the construction industry, as it involves accurately predicting the cost of a project before work begins. Within Australia and New Zealand, construction estimating...

article-image

RFQs Explained: How Contractors Prove Their Qualifications

In the construction industry, the term RFQ can mean two very different things: a request for qualifications, or a request for quote.  When an owner-developer uses a request for qualifications...

article-image

RFIs: A Contractor’s Guide to Requests for Information

Head contractors spend a lot of time waiting for owner-developers to respond to their requests for information (RFI). So much so, that if they were to add up all the...

Procore is committed to advancing the construction industry by improving the lives of people working in construction, driving technology innovation, and building a global community of groundbreakers. Our connected global construction platform unites all stakeholders on a project with unlimited access to support and a business model designed for the construction industry.

LinkedIn Icon
LinkedIn
Facebook icon
Facebook
Twitter icon
Twitter
Instagram Icon
Instagram
YouTube icon
YouTube

Call us at 1800 431 456 to speak with a product expert.

Apple LogoApple App StoreGoogle Play logoGoogle Play

Downloads

Apple LogoApple App StoreGoogle Play logoGoogle Play
  • Privacy Notice
  • Terms of Service
  • Australia Privacy

© 2024 Procore Technologies, Inc.