Custom Workday Calendars and Modernized Scheduling Settings

Versiones futuras5 jun 2026

Admins can now create and manage project-specific Workday calendars — defining working hours per day, working days per week, non-working holidays, regional holiday presets (e.g., US, UK), and date-specific exception hours — for more accurate schedule calculations on site. Scheduling also features a redesigned settings experience aligned to Procore's modern design system. Per-schedule settings (start date, default calendar) are isolated from project-level settings to support multi-schedule projects, and admins get global "Start Over" and per-lookahead deletion controls. User permissions continue to live in the Directory.